Close your eyes....
*
*
Open your eyes....
*
*
Look! Brick!!!
After many many hours of driving around and many different choices being shot down (out of stock, doesn't lay right, not enough bricks, etc...) we FINALLY have brick at our house!
And garage doors!
Plaster was also started this week! The plasterer thinks he'll be done in 8 - 10 days so we're looking at a completely plastered house by the end of next week!
The north side of the house (bedrooms, master bath, kid's bath) were complete by the end of the week!
And the rest of the brick supplies were delivered. Brick layer call tonight (Saturday) to say he'd be there at 7:00 am on Tuesday morning to get started. It should take 10 business days to lay all 10,000 bricks.
Plaster board was hung going down the garage steps
Ductwork in the basement...
I had to take this picture because Jay said we would NEVER have a window unit in our new house!
Coming up next week: Paint choices, finalize lights and fireplace marble, more plaster work and BRICK!!! Estimated move in date is Oct 1!